January 2011
The designer has refined the wall bracing project of the existing concert hall. There have been made additional opencast works
Read moreThe designer has refined the wall bracing project of the existing concert hall. There have been made additional opencast works
Read moreThe Financial Department of the Ministry of Culture and National Heritage (MKiDN) has checked the Appendix no. 2 to the
Read moreOn March 3, 2011, the Silesian Province?s Conservator of Monuments has issued the Permit to carry out the building’s bracing
Read moreAt the beginning of April hacking off plaster and ceilings? disassembly were finished. It has been decided that piling from
Read moreIn August 2011, the General Contractor finished the construction of 80% of the brick walls in the new part of
Read moreBy the end of September 2011, the General Contractor finished the construction of the new part of the building. 100
Read moreBy the end of October 2011 the General Contractor had made 95% of horizontal distribution pipes and 95% of vertical