August 2012

In August 2012 the general contractor ? Mostostal Warszawa SA ? placed the ground slab in the area of the stage in the existing building, executed installation canals in the basement, continued the grout works in the basement and on the ground floor and reinforced the ceiling over the first floor. In the added part, the general contractor completed plastering the walls, continued to execute the floors and prepared the surfaces for the lining on the 1st and 2nd level. The installation works on the water supply and sewerage network, central heating, ventilation, as well as electric works were continued. 
The total net value of the works completed in August 2012 reached PLN 911,546.31. 
On 1, 8 and 29 August 2012 technical councils on the site were held. 
On 31 August 2012 the company of PPU Agrocom sp. z o.o. filed a replacement design of the boiler house.