September 2012

In September 2012 the general contractor ? Mostostal Warszawa SA ?continued the grout works in the existing building, concreted the steel posts installed, strengthened the ceilings over the ground floor and the first floor, disassembled the ceiling over the second floor and the roofing. In the added part of the building it completed the ceiling reinforcement in the chamber music hall and was concreting the ceiling. It continued the works on the water supply and sewerage, central heating, ventilation and electrical installations. In the garage 30% of the door metalwork was completed. 
The total net value of the works executed in September 2012 reached PLN 1,003,201.80. vOn 5, 12, 21 and 28 September 2012 technical councils were held at the construction site, attended by the contractor, the designer, the Contract Engineer and the investor. The designer was coordinating the discipline-specific designs with the fire protection specialist. 
On 19 September 2012 a site inspection was held, attended by the representatives of Katowickie Wodociągu S.A. (water supply company), which resulted in the specification of the date of executing the connection for 31 May 2013.
On 11 September 2012 the Executive Board of the Province of Silesia resolved the increase of the estimated value of the project to the amount of PLN 48,379,704 and securing the funds missing in 2013 for the completion of the project in the amount of PLN 8,498,616. 
On 14 September 2012 Bogdan Zdrojewski, the Minister of Culture and National Heritage, signed an annex No. POIS.11.02.00-00-036/08/03 to the contract on the financial support for the project, changing the date of completing the project to 30 November 2013 and updating the appendixes to the contract. 
On 27 September 2012 a project inspection carried out by the Marshal Office of the Province of Silesia was commenced.