January 2014
The construction closing to its end, in January the works of the General Contractor in the existing building comprised finishing
Read moreThe construction closing to its end, in January the works of the General Contractor in the existing building comprised finishing
Read moreIn the existing building the works in the area of the roof and the patio were continued; floors, horizontal insulation
Read moreIn February 2013 the scope of works in the existing building covered demolition works, walls strengthening with shotcrete, execution of
Read moreAt the construction site the scope of works in the existing building comprised the execution of walls, partitions and casings,
Read moreIn April 2013 in the existing building the works connected with the execution of walls and partitions, shortcreting, internal plasters,
Read moreAt the construction site at 2 Sokolska street the General Contractor was executing the following works in the existing building:
Read moreIn September at the construction site within the building the works comprised: the roof and the patio, internal plasters, gypsum