July 2011
On the 12th July 2011 the investor received an updated geodetic map for the project?s purposes, prepared by the company
Read moreIn August 2011, the General Contractor finished the construction of 80% of the brick walls in the new part of
Read moreBy the end of September 2011, the General Contractor finished the construction of the new part of the building. 100
Read moreBy the end of October 2011 the General Contractor had made 95% of horizontal distribution pipes and 95% of vertical
Read moreBy the end of November 2011, the General Contractor performed 100 % of the assembly works of the frames for
Read moreIn December 2011 the General Contractor completed the process of windows fitting in the new section and completed the third
Read moreStrengthening of the building?s foundations is being continued by the jet-grouting method. It consists in injecting concrete into openings (0,7
Read moreThe extension and the revonation of the building are being carried out in agreement with the schedule. In November, several
Read moreBuilding works are being carried out according to the schedule. Floors and non-renovated parts of the building have been protected