February 2013

In February 2013 the scope of works in the existing building covered demolition works, walls strengthening with shotcrete, execution of walls and partitions. Floors, horizontal insulation and installation channels were executed. Construction works were completed, especially reinforced concrete cores, reinforced concrete walls, substrings, poles, crowns, steel structures with anti-fire protection. The ceilings over the ground and the first floor were strengthened, staircases and ventilation channels were made and the lift shaft was raised. Works in the area of the roof and the patio were being continued. In the added part the walls were finished with plaster, facing and painted, interiors were provided with décor elements, ventilation installation and water supply and sewerage installation were executed. Installation works in the transformed station were progressing.
The General Contractor accepted the time for installing the organ from 5 to 31 August 2013, which had been specified together with the company of Schuke.