August 2012
In August 2012 the general contractor ? Mostostal Warszawa SA ? placed the ground slab in the area of the
Read moreIn August 2012 the general contractor ? Mostostal Warszawa SA ? placed the ground slab in the area of the
Read moreIn September 2012 the general contractor ? Mostostal Warszawa SA ?continued the grout works in the existing building, concreted the
Read moreIn October 2012 the General Contractor ? Mostostal Warszawa SA ? continued the works in the existing building: over 50%
Read moreIn November 2012 the financial advancement of the contract on the continuation and completion of the construction works of the
Read moreThe designer has refined the wall bracing project of the existing concert hall. There have been made additional opencast works
Read moreThe Financial Department of the Ministry of Culture and National Heritage (MKiDN) has checked the Appendix no. 2 to the
Read moreOn March 3, 2011, the Silesian Province?s Conservator of Monuments has issued the Permit to carry out the building’s bracing
Read moreAt the beginning of April hacking off plaster and ceilings? disassembly were finished. It has been decided that piling from