December 2013

In December 2013 the works of the General Contractor in the existing building comprised: floors and horizontal insulations; roofs; staircases

Read more

March 2012

After conclusion on February 27 2012 of a contract for the continuation and completion of construction works related to the

Read more

April 2012

In April the General Contractor – Mostostal Warszawa S.A. – continued demolition and earth works in the existing building ?

Read more

May 2012

In May 2012 the general contractor – Mostostal Warszawa SA – continued construction (demolition and concrete reinforcement) works in the

Read more

June 2012

In June the General Contractor ? Mostostal Warszawa SA ? continued construction works in the existing building.  The following works

Read more