October 2013
The works of the General Contractor in the existing building comprised: the roof and the patio, internal plasters, gypsum finish,
Read moreThe works of the General Contractor in the existing building comprised: the roof and the patio, internal plasters, gypsum finish,
Read moreIn November 2013 the works of the General Contractor in the existing building comprised: the roof and the patio, internal
Read moreIn December 2013 the works of the General Contractor in the existing building comprised: floors and horizontal insulations; roofs; staircases
Read moreNo construction works related to the project were performed in January 2012. A tender for the Contract Engineer was successfully
Read moreOn February 16 2012 the winning tender for the continuation and completion of construction works related to the project, was
Read moreAfter conclusion on February 27 2012 of a contract for the continuation and completion of construction works related to the
Read moreIn April the General Contractor – Mostostal Warszawa S.A. – continued demolition and earth works in the existing building ?