June 2012
In June the General Contractor ? Mostostal Warszawa SA ? continued construction works in the existing building.
The following works were performed: demolition in axes 12/14-15, reinforced concrete works in walls 1-12, reinforcement of the ground and first floor ceilings in axes 1-14, spraying with concrete, floors and horizontal insulations, installation conducts, internal walls, partition walls, internal plasters, gypsum finish and wall painting, electrical installations, switchgear and internal power line assembly, low current installation, sanitary works, plumbing and heating system installation, ventilation. The total net value of the construction works performed in June 2012 amounted to PLN 1 020 942.
On June 13 and June 27 2012 technical committees with the participation of the General Contractor, the contract engineer and representatives of the investor and of the Marshal’s Office held their meetings at the construction site.
On June 27 2012 the construction site was inspected by a representative of the Silesian Provincial Conservator of Monuments