December 2012
The net value of the construction works executed in December 2012 amounted to PLN 3,230,000.00.
In the additional storey of the building, the works were continued in the area of the roof and the patio, the flooring and the horizontal insulation, as well as the metalwork.
In the added part the elevation was insulated with the application of the Baumit system.
The electric, low voltage and sanitary installation works were continued in the whole building.
On 5, 12 and 19 December 2012 technical councils were held on the site with the participation of the Contractor, the Designer, the Contract Engineer and the Investor.
The date of the commencement of the installation of the organ in the edifice of the Silesian Philharmonic was set with the company of Schuke BerlinerOrgelbauwerkstatt GmbH for 2 September 2013.
As of the end of December 2012 the financial advancement of the contract on the continuation and completion of the construction works in the project reached 40.21% of the contractual value, whereas the total financial advancement of the Project amounted to 52.20% of the value specified in the agreement on the financial support for the project within the framework of the Operational Programme Infrastructure and Environment.