January 2011
The designer has refined the wall bracing project of the existing concert hall. There have been made additional opencast works aimed at verification of bearers’ strength before setting about the construction’s reinforcement. At the end of January the wall bracing process has begun, and after that strengthening of the building?s foundations will be continued by the jet-grouting method. The range of additional works have been agreed on with the Silesian Province?s Conservator of Monuments. We are waiting for signing the Appendix no. 2 to the agreement of financial support on the project, and this postpones the date of the investment’s realization until June 2012.